Municipal Projects
The following municipal projects are currently under development:
Northville Hills Pressure District Improvement
Five Mile Water Main Replacement
Pickford Water Main
Replacement Project
Hills of Crestwood Detention Basin
Maintenance
Seven Mile Road Sanitary Sewer Extension
Homer Road Sanitary Sewer Extension
Northville
Hills Pressure District Improvements
Elevated Tank, Booster Station and Water Distribution
Northville
Township has awarded contracts for water distribution system
improvements to create a new pressure district for an area in the
township currently experiencing low water pressure. This area is
generally bounded to the south by 5 Mile Road, to the east by Sheldon
Road, to the north approximately 1/2 mile north of Six Mile Road, and
to the west by approximately 1/2 mile west of Beck Road. In order to
create the new pressure district, a new elevated water tank, a booster
station and water main distribution system improvements will be
constructed.
The purpose of the new pressure district is to alleviate low water
pressures experienced by existing residents and to be proactive in
dealing with future pressure issues as new users are added to the
existing water system. This will also ensure adequate future fire
flows are available in high demand situations, such as during the
summer months when irrigation demand/use is added to the system.
The new pressure district will be supplied with water from the City
of Detroit stored in the new elevated water tank. The tank will
be constructed by the Chicago Bridge and Iron Company at a cost of
$1.7 million and have a capacity of storing one million gallons of
water. The tank will be located within the Community Park, near the
future Water and Sewer Maintenance Building. The tank will be filled
by the new booster station.
The booster station will consist of pumps that will pump water from
the Detroit Water source to the elevated water tank. A contract has
been awarded to Sorenson Gross Construction Company in the amount of
$1.7 million. The booster station will be located on the
commercial property situated on the north east corner of the Five Mile
Road – Sheldon Road intersection.
The water main system improvements contract has been awarded to
Stante Excavating Company in the amount of $600,000 and includes
constructing new water mains at the following locations:
- 1,000 feet of 8-inch water main along Six Mile Road, between
Sheldon Road and Meadow Crest North.
- 400 feet of 12-inch water main between the Northville High
School and the Woodlands North subdivision.
- 700 feet of 12-inch water main along Six Mile Road, between
Stonebrook Drive and Hilltop View Drive.
- 1,650 feet of 12-inch water main along Six Mile Road, between
Sherwood Land and a point approximately 700 feet east of Beck Road.
- 3,200 feet of 16-inch water main along Five Mile Road and within
Community Park between Beck Road and the Arcadia Ridge development.
SCHEDULE
Our anticipated project schedule and milestones are as follows:
- Begin Construction: April 2007
- Project Completion: June 2008
The Township is constructing a $500,000 water main project to
replace approximately 2,000 feet of water main along Five Mile Road,
between the Northville Forest Apartment complex and Tanger School. The
existing main is cast iron and has chronic water main breaks, as
recent as early 2006.
The construction contract was awarded to Rainbow Construction
Company in April and work began in late May. The contractor
anticipates completion in early July.
Project Map
Pickford
Water Main Replacement Project
Northville Township is in the preliminary design phase of a water
main replacement project that will extend from the Fox Hollow
Subdivision to Sheldon Road. This project is being financed entirely
by the township and no individual property will be assessed.
Phase I of the project will extend from the Fox Hollow Subdivision
(tying into an existing water main between lots 12 and 13) to Pickford
Road where it will continue in the right of way to an end location in
Fermanagh Court. Phase I will consist of approximately 2,800 ft
of 12” ductile iron pipe.
The purpose of the improvement project is to provide a replacement
ductile iron water main for an old cast iron water main that runs
cross country through lots from Fox Hollow to Sheldon Road. The
existing main is exposed in locations, and subject to future breaks
due to its age. This project will upgrade the pipe material,
provide additional service opportunities, as well as place the water
main in a location easily accessible for future maintenance.
Preliminary design has been completed and easement acquisition is
underway.
SCHEDULE
No schedule has been determined for this project.
Project Map
Hills of Crestwood Detention Basin
Maintenance
Northville Township has been requested by the Hills of Crestwood
Homeowner Association to assist in the maintenance of their detention
pond. All homeowners in the association will receive a one time
assessment for the management, engineering and construction cost
associated with the project. The assessment will be placed on
the winter tax bill at project completion.
The $40,000 construction contract was awarded to Anglin Civil
Constructors in April and work is underway. It is anticipated
that the construction will be completed by the end of June.
Seven Mile Road Sanitary Sewer Extension
The Board of Trustees authorized proceeding with the design and
construction of approximately 850 feet sanitary sewer along the north
side of Seven Mile Road commencing at the west edge of the Windridge
Subdivision, westerly to the second lot west of Meadowbrook Drive on
Seven Mile Road. The project will be funded in part by a
property owner who is constructing a new home on this lot.
The $90,000 project was awarded to Stante Excavating in April and
work began in early June. Completion is expected in July.
Project Map
Homer Road Sanitary Sewer Extension
The Board of Trustees authorized proceeding with the design and
construction of approximately 175 feet sanitary sewer from the East
Northville Hills Subdivision to the west end of Homer Road. An
existing home has a failed septic system and has qualified for
Community Block grant funding to connect to the sewer.
The estimated cost for the sewer is $65,000. Township staff designed
the sewer and the project is presently out for bids. It is
anticipated a contractor will be selected in July and the work will be
performed in August.
Project Map

Northville Township
44405 Six Mile Rd.
Northville, MI. 48168
(248) 348-5800
Contact the Township Webmaster by
clicking here.
To report technical problems with this website, please
click here.
|
|
|
| |
|
|
Site designed and
maintained by

|
If you have trouble viewing Adobe documents,
click here
to download the free Adobe Reader.


|
Our website is
Section 508 compliant.


|
|